Spruce Production Division Railroads
 | 
| 
 
Spruce Production Railroad No. 1 
Name:   Clallam County Railroad 
District:   Clallam County District   
Main Line Completed:   36 Miles 
Spurs Completed:   0 Miles 
Sidings Completed:   NR 
 | 
 
Spruce Production Railroad No. 2   
Name:   Merrill & Ring Railroad 
District:   Clallam County District 
Main Line Completed:   4.69 Miles   
Spurs Completed:   2.19 Miles 
Sidings Completed:   NR 
 
 | 
| 
 
Spruce Production Railroad No. 3   
Name:   Quinault Railroad 
District:   Quinault District 
Main Line Completed:   5.322 Miles   
Spurs Completed:   0.254 Miles 
Sidings Completed:   0.189 Miles 
 
 | 
 
Spruce Production Railroad No. 4   
Name:   Elk River Railroad 
District:   Grays Harbor District 
Main Line Completed:   2.14 Miles  
Spurs Completed:   0.82 Miles 
Sidings Completed:   0.284 Miles 
 
 | 
| 
 
Spruce Production Railroad No. 5   
Name:   North Nemah Railroad 
District:   Willapa Bay District 
Main Line Completed:   7.73 Miles     
Spurs Completed:   0.218 Miles 
Sidings Completed:   1.163 Miles 
 
 | 
 
Spruce Production Railroad No. 6   
Name:   South Nemah Railroad 
District:   Willapa Bay District 
Main Line Completed:   2.282 Miles 
Spurs Completed:   1.618 Miles 
Sidings Completed:   NR   
 
 | 
| 
 
Spruce Production Railroad No. 7   
Name:   Nasel River Narrow Gauge 
District:   Willapa Bay District 
Main Line Completed:   1.887 Miles  
Spurs Completed:   0.171 Miles 
Sidings Completed:   NR 
 
 | 
 
Spruce Production Railroad No. 8    
Name:   Lewis & Clark Narrow Gauge 
District:   Clatsop District 
Main Line Completed:   2.5 Miles   
Spurs Completed:   NR   
Sidings Completed:   NR 
 
 | 
| 
 
Spruce Production Railroad No. 9  
Name:   Lewis & Clark River Railroad 
District:   Clatsop District 
Main Line Completed:   13 Miles 
Spurs Completed:   5.257 Miles 
Sidings Completed:   2.103 Miles 
 
 | 
 
Spruce Production Railroad No. 10   
Name:   Toledo & Wessel Creek Railroad 
District:   North Yaquina District 
Main Line Completed:   6.4 Miles  
Spurs Completed:   1.74 Miles 
Sidings Completed:   0.14 Miles 
 
 | 
| 
 
Spruce Production Railroad No. 11   
Name:   Yaquina Northern Railroad 
District:   North Yaquina District 
Main Line Completed:   10.83 Miles   
Spurs Completed:   2.09 Miles 
Sidings Completed:   2.74 Miles 
 
 | 
 
Spruce Production Railroad No. 12   
Name:   Alsea Southern Railroad 
District:   South Yaquina District 
Main Line Completed:   23.424 Miles   
Spurs Completed:   0 Miles 
Sidings Completed:   2.567 Miles 
 
 | 
| 
 
Spruce Production Railroad No. 13   
Name:   Beaver Hill Railroad 
District:   Coos Bay District 
Main Line Completed:   1.544 Miles   
Spurs Completed:   0.047 Miles 
Sidings Completed:   0.196 Miles 
 
 | 
  
 | 
| 
 
<< BACK
 
 
Andrew Craig Magnuson 
Forks, Washington 
April 14, 2007 
 
Copyright © by Andrew Craig Magnuson 
 
 |